Health Care


ProMedica Wildwood Orthopaedic and Spine Hospital >> Toledo, OH

  • 130 kW electricity
  • 0.8 MMBTU hot water

Veterans Affairs Hospital >> Ann Arbor, MI

  • 1000 kW Electricity
  • 2.0 MMBTU Steam (75psi)

Rome Memorial Hospital >> Rome, NY

  • 260 kW Electricity
  • 1.6 MMBTU Hot Water

Entertainment


tma-interior
Toledo Museum of Art >> Toledo, OH

Installed a CHP system featuring four C65 Capstone microturbines with hot water heat recovery modules and remote natural gas compressors. The units interface directly with the existing hot water system and electrical distribution to provide supplemental heat and on-site power.

RESULTS: Under low load conditions, the turbines generate enough heat and power to meet the loads of the entire facility.

  • 260 kW Electricity
  • 1.6 MMBTU Hot Water
  • Power Reliability
  • Facility back-up power

Toledo Museum of Art Phase 2 – Glass Pavilion >> Toledo, OH

  • 130 kW Electricity
  • 0.8 MMBTU Hot Water
  • 20 Tons Chilled Water

huntington-interior
Huntington Center >> Toledo, OH

To supplement Huntington Center’s heating, cooling and electricity needs, GEM Energy installed a CHP system integrating four C65 Capstone microturbines with hot water heat recovery modules, natural gas compressors, and an absorption chiller.

RESULTS: The turbine array runs year round to produce electricity. In the winter, the exhaust energy is recovered to provide heating for the facility; and in the summer, this energy is used to drive an absorption chiller. Under low load conditions, the system generates enough heat and power to meet the loads of the entire facility.

  • 260 kW Electricity
  • 1.6 MMBTU Hot Water
  • 82 Tons Chilled Water

SeaGate Convention Centre >> Toledo, OH

  • 260 kW Electricity
  • 1.6 MMBTU Hot Water
  • 100 Tons Chilled Water
  • Facility back-up power

Waste Water Treatment Plants (WWTP)


>> Twinsburg, Ohio

  • 65 kW electricity
  • 250 MBTU hot water
  • Biogas-fueled system

>> Lima, OH

  • 130 kW electricity
  • 500 MBTU hot water
  • Biogas-fueled system

>> Ithaca, NY

  • 260 kW Electricity
  • 1.2 MMBTU Hot Water
  • Renewable Power System

>> Jamestown, NY

  • 65 kW Electricity
  • 0.3 MMBTU Hot Water
  • Renewable Power System

Higher Education


Oakland University >> Rochester, MI

  • Commissioning scheduled for July, 2014
  • 400 kW electricity
  • Two heat exchangers totaling 1.83MM BTUs/hour of heat recovery for Hot Water
  • Facility back up power

SUNY College of Environmental Science and Forestry >> Syracuse, NY

  • 195 kW Electricity
  • 1.0 MMBTU Steam (15 psi)
  • Facility back-up power

University of Toledo, Center for Visual Arts >> Toledo, OH

  • 130 kW Electricity
  • 0.8 MMBTU Hot Water

syracuse-exterior
Syracuse University Data Center >> Syracuse, NY

The Combined Cooling, Heating and Power (CCHP) system includes 12 Capstone C65 Hybrid UPS turbines that run off natural gas, function as uninterruptible power supplies and produce 65 kilowatts of power each. The center produces its own heating and cooling by recovering the turbine waste heat. Absorption chillers are used to make cold water to directly cool the computer servers.

RESULTS: The data center has its own onsite power plant, and estimates that it uses 50 percent less energy than a typical data center of its size. It is able to operate off-grid due to the tri-generation system. Syracuse University’s data center is one of the “greenest” data centers in the world.

  • 780 kW Electricity
  • 300 Tons Chilled Water
  • 4.0 MMBTU Hot Water
  • Mission Critical Power System
  • Battery-backed up Uninterruptible Power System (UPS)

ut-modular-interior

University of Toledo Data Center >> Toledo, OH

Our modular power systems incorporate all the features and benefits of an integrated mission critical power system in a space conscious pre-engineered container system. These modules are easily shipped to any location and are capable of being connected to existing infrastructure in a shorter period of time.

Ohio Third Frontier awarded a $1 million hybrid loan toward this project’s design, implementation and commercialization. Ohio Third Frontier, of the state of Ohio’s Development Services Agency, provides funding to Ohio technology-based companies, universities, nonprofit research institutions, and other organizations to create new products, companies, industries and jobs.

RESULTS: The completed University of Toledo modular unit is the second green data center in the nation and the first in Ohio. The new power system will reduce by 50% the amount of fossil fuel needed to power the University’s data center.

  • 260 kW Electricity
  • 100 Tons Chilled Water
  • 1.0 MMBTU Hot Water
  • Modular Mission Critical Power System
  • Battery-backed up UPS

Commercial


Pearl Valley Cheese >> Fresno, OH

  • 65 kW electricity
  • Renewable power system

Dominion East Ohio Corporate Headquarters Complex >> Cleveland, OH

  • 1000 kW Electricity
  • Power reliability
  • Facility back-up power

MathWorks Data Center >> Boston, MA

  • 260 kW Electricity
  • 100 Tons Chilled Water
  • 1.0 MMBTU Hot Water
  • Grid connect only system